Sub panel in detached building: new construction

Merry Christmas
Status
Not open for further replies.

nmjake

Member
Location
New Mexico
Occupation
Owner-Builder
I know this topic has been discussed extensively a while ago, but I'd appreciate any updates with more modern code revisions. I'm an owner-builder in New Mexico (NEC 2020). New construction of a new detached building, power coming through a feed from the main service panel 100' away. Based on what I'm reading in the code and on this forum, my plan is included a grounding conductor in the feed coming from the service panel (2 hots, 1 neutral, 1 grounding), add a new grounding electrode at the new construction, and not bond the ground and the neutral in the new sub panel. Sound right? Thanks!
 