Will Wire
Senior Member
- Location
- California: NEC 2020
- Occupation
- Electrical Contractor
The situation: Residential. I installed a 12/24 Load Center on a detached building. I am using a back fed breaker for the Disconnect. I also have Surge Protection. When I install the back fed disconnect breaker, I also loose the two spots horizontally next to it because of the hold-down bracket. When I installed Surge Protection, I lost two more breaker spots. In total I loose six one-inch Breaker spots.
Question: Is it NEC compliant to route the existing panel feed wires, through the existing load center in question, and mount a new Panel next to it to house the disconnect Breaker and the Surge Protection, then return from the disconnect back to the 12/24 load center. This would allow me to reclaim the 6 Breaker spots.
I am in the 2020 NEC.
Thank you,
Trent
Question: Is it NEC compliant to route the existing panel feed wires, through the existing load center in question, and mount a new Panel next to it to house the disconnect Breaker and the Surge Protection, then return from the disconnect back to the 12/24 load center. This would allow me to reclaim the 6 Breaker spots.
I am in the 2020 NEC.
Thank you,
Trent