• We will be performing upgrades on the forums and server over the weekend. The forums may be unavailable multiple times for up to an hour each. Thank you for your patience and understanding as we work to make the forums even better.

Subpanel Disconnect at detached building.

Will Wire

Senior Member
Location
California: NEC 2020
Occupation
Electrical Contractor
The situation: Residential. I installed a 12/24 Load Center on a detached building. I am using a back fed breaker for the Disconnect. I also have Surge Protection. When I install the back fed disconnect breaker, I also loose the two spots horizontally next to it because of the hold-down bracket. When I installed Surge Protection, I lost two more breaker spots. In total I loose six one-inch Breaker spots.

Question: Is it NEC compliant to route the existing panel feed wires, through the existing load center in question, and mount a new Panel next to it to house the disconnect Breaker and the Surge Protection, then return from the disconnect back to the 12/24 load center. This would allow me to reclaim the 6 Breaker spots.

I am in the 2020 NEC.

Thank you,

Trent
 

LarryFine

Master Electrician Electric Contractor Richmond VA
Location
Henrico County, VA
Occupation
Electrical Contractor
Yes, although I would likely opt for a larger single panel. Tandems in this panel wouldn't be enough?

You could also leave the main and surge breakers in this panel and put your circuits in a sub-panel.

That way, you would only have to extend smaller wires to the sub-panel instead of the feeder itself.
 

infinity

Moderator
Staff member
Location
New Jersey
Occupation
Journeyman Electrician
Personally I would use a different panel. What panel needs 4 slots for a back-fed main CB?
 

LarryFine

Master Electrician Electric Contractor Richmond VA
Location
Henrico County, VA
Occupation
Electrical Contractor
Personally I would use a different panel. What panel needs 4 slots for a back-fed main CB?
Main and surge breakers. The main eats for spaces, the surge two.

That leaves 6/12 spaces/circuits, respectively.

Wait, is the surge in the breaker, or does it feed one?
 

Will Wire

Senior Member
Location
California: NEC 2020
Occupation
Electrical Contractor
The panel is already installed. It is a Siemens SNW1224L1125. When you install the hold-down bracket for the back-fed breaker it won't allow breakers in the horizontal spaces next to it. I am considering changing the whole panel. I was looking for different NEC compliant options. I appreciate all the input.
 

infinity

Moderator
Staff member
Location
New Jersey
Occupation
Journeyman Electrician
The panel is already installed. It is a Siemens SNW1224L1125. When you install the hold-down bracket for the back-fed breaker it won't allow breakers in the horizontal spaces next to it.
That's a terrible design.
 

Will Wire

Senior Member
Location
California: NEC 2020
Occupation
Electrical Contractor
It looks like it would. The one they are making now is a little different. I called Tech Support to see if I was doing something wrong. I was told no. The one I have, which is the accessory listed on the panel door does prevent breakers next to it. The new on has a larger protrusion and a screw.
 
Top