Hello all,
We recently finished a wind re-power project which included some modification to the existing collector substation such as, addition of SCADA, new CTPT combo, ground grid extension. At the end of the project, question came up about performing ground grid test/Fall of potential test as the existing fence was moved about 20 feet and ground grid was extended and tied to the existing grid. Is it a requirement to perform FoP test if there is a modification to the grid? I believe it was left out of the scope assuming that the over all existing ground grid must have already been tested and we're only tying into it which would only improve the split factor and make the grid more stringent.
Thanks in advance for any feedback.
We recently finished a wind re-power project which included some modification to the existing collector substation such as, addition of SCADA, new CTPT combo, ground grid extension. At the end of the project, question came up about performing ground grid test/Fall of potential test as the existing fence was moved about 20 feet and ground grid was extended and tied to the existing grid. Is it a requirement to perform FoP test if there is a modification to the grid? I believe it was left out of the scope assuming that the over all existing ground grid must have already been tested and we're only tying into it which would only improve the split factor and make the grid more stringent.
Thanks in advance for any feedback.