timm333
Senior Member
- Location
- Minneapolis, MN
- Occupation
- Electrical Design Engineer
I have a question about underground cables of 13.8kV substation. There will be ground-grid whose depth would be 24”, and underground 13.8kV cables whose depth would be 30”. Does it mean that the cables will have to be buried before the ground-grid is installed? Or should we lay conduits below the ground-grid, and then the cables can be pulled in conduits later after the ground-grid is installed? Thanks.