I have a 20KW heat strip that’s been installed in an air handler for a Geo thermal system.
Nameplate on strip is 111.4 A MCA and 125A MOCP.
I planned on using a 125A circuit breaker in a 2 space main lug load center as the disconnect means.
Do I still need to add the 25% factor or is the MOCP if 125A all the larger it has to be?
My wire size is #2THHN
Thank you.
Nameplate on strip is 111.4 A MCA and 125A MOCP.
I planned on using a 125A circuit breaker in a 2 space main lug load center as the disconnect means.
Do I still need to add the 25% factor or is the MOCP if 125A all the larger it has to be?
My wire size is #2THHN
Thank you.