Oooh.
I just got multiple quotes of 4-6 months for a two meter service entrance pack.
Anyone else seeing this? Have suppliers that have something in stock?
This is for California, within the PG&E territory (whatever style meter PG&E uses).
The Eaton selector shows zero suitable meters:
Possible model numbers:
UT2R2122B MP22125 WP2211RJ 1MP2204RC
I just got multiple quotes of 4-6 months for a two meter service entrance pack.
Anyone else seeing this? Have suppliers that have something in stock?
This is for California, within the PG&E territory (whatever style meter PG&E uses).
The Eaton selector shows zero suitable meters:
Possible model numbers:
UT2R2122B MP22125 WP2211RJ 1MP2204RC