I have a 200A service panel with a 200A main breaker in the panel, the neutral bar and ground bar are separate, neutral bar and enclosure are bonded through a green screw. There is a nipple between the meter and the service panel, a bonding bushing is installed in the service panel. I think I need to connect the ground from the bonding bushing lug to the neutral bar directly but since the neutral bar and ground bar are bonded in the service panel, does Code allow the supply side bonding jumper to be landed on the ground bar with all other branch circuit EGCs?