I'm trying to determine if a run of 5" RMC can be supported every 20' or 10' in accordance with 344.30(B). It is approximately 80 feet in total length, with a single 90º sweep in the middle. Do each of the lengths on either side of the sweep count as "straight" - thus allowing me to use Table 344.30(B)(2) - or is the whole thing a single non-straight run (thus requiring support every 10 feet). (Note: I'd prefer to support it every 10', but need a convincing argument to make this happen!).
Also, does a transition from the RMC to LFMC count as a "termination" in regards to securing the RMC within 3' of this point in accordance with 344.30(A)(1)?
Long time lurker, first time poster, thanks!
Also, does a transition from the RMC to LFMC count as a "termination" in regards to securing the RMC within 3' of this point in accordance with 344.30(A)(1)?