DMeigs
Member
- Location
- Albuquerque, New Mexico, USA
Hey Everyone,
I have an application that calls for 3 #2/0, 1 #6 ground (individual conductors or cable) in an existing 2" RGS conduit system installed along a pipeline at a steep incline, and I am concerned about how to support the conductors. The installation is approximately 1600 feet long with a vertical drop of about 1100 feet. The conduit has a few boxes along the way, but they have up to 320 feet of elevation change between them. If this was a vertical raceway, Article 300.19 would require me to support the (copper) conductor every 80 feet. Does 300.19 apply to conduit on a slope as well?
If 300.19 does not apply, at what interval should the conductors be supported?
Thanks!
I have an application that calls for 3 #2/0, 1 #6 ground (individual conductors or cable) in an existing 2" RGS conduit system installed along a pipeline at a steep incline, and I am concerned about how to support the conductors. The installation is approximately 1600 feet long with a vertical drop of about 1100 feet. The conduit has a few boxes along the way, but they have up to 320 feet of elevation change between them. If this was a vertical raceway, Article 300.19 would require me to support the (copper) conductor every 80 feet. Does 300.19 apply to conduit on a slope as well?
If 300.19 does not apply, at what interval should the conductors be supported?
Thanks!