Alwayslearningelec
Senior Member
- Location
- NJ
- Occupation
- Estimator
doing this small renovation job where they demo walls and ceilings and putting up new walls and hung gyp ceilings . There’s some existing mc cables in ceiling that we are connecting to and some new that we’re running. My foreman decided to use installed anchors and rods into the slab to support the existing cables that were hanging and also some of the new. Well the GC os saying these were not submitted and approved but I was not aware he was doing this. I figured we’d supporting of the black iron rod that goes to the slab as we usually do with caddy KX type of clip. He said that the ceilings weren’t up yet so he couldn’t do that but normally would. This is where my lack of “install” experience comes in and knowing sequence. Is there anything he could’ve done to hold off driving all these anchors and rods to support the mc cable( this is small 12/2 stuff) until the ceiling went up? So there are two aspects to this …. First supporting the existing MC cable that’s up there and then supporting the new that he’s installing . Can you wait til the ceiling framing/ rods etc. go up before you run your mc cable so then you have something to support to?