We are replacing zinco panels in a apartment building which is 35 years old.
When the apartments were wired they ran the switchleg for the hallway light thru the panel then to the light switch beside the panel.
The inspector told me that the switchleg will have to be removed from the panel.
He didn't state a code article and i can't find it in the NEC that it can't be there.
When the apartments were wired they ran the switchleg for the hallway light thru the panel then to the light switch beside the panel.
The inspector told me that the switchleg will have to be removed from the panel.
He didn't state a code article and i can't find it in the NEC that it can't be there.