Jimmy7
Senior Member
- Location
- Boston, MA
- Occupation
- Electrician
The owner of a project we’re working on hired their own engineer to review the proposed drawings. Currently, drawings show a SWBD-Main labeled “Service Disconnect”, and there is also separate switchboard labeled “SWBD-Dist”, both switchboards are in the same building. On the schedule SWBD-Dist is listed as Main Lug Only. The owner’s engineer is stating that the SWBD-DIST requires a main circuit breaker. I don’t think a main breaker is needed, am I correct on this?
This engineer also is suggesting that the generator switchboard (SWBD-Gen) have a main breaker as well. This switchboard currently only has the ability to have six breakers maximum. Since it can only have six breakers a main wouldn’t be needed, correct?

This engineer also is suggesting that the generator switchboard (SWBD-Gen) have a main breaker as well. This switchboard currently only has the ability to have six breakers maximum. Since it can only have six breakers a main wouldn’t be needed, correct?
