I'm planning to install a 13.2 kV/ 480 Volt 2500 KVA transformer, 3000 Amp switchgear (480 V) and 6 VFD drive cabinets.
1. 13.2 kV/ 480 Volt, 2500 KVA transformer will be located outside the manufacturing plant. This transformer will feed a 3000 Amp switchgear rated for 480 V.
2. This switchgear has 6 breakers that will feed 6 drive cabinets. All 6 drive cabinets will be installed inside a MCC room.
3. My question is regarding switchgear installation location. Is it acceptable to install this 3000 Amp switchgear inside MCC room or does it have to be installed in a separate switchgear room ? Please note that MCC room already has a Distribution Panel (DP) fed by another transformer/ switchgear. In addition, MCC room will have many drive cabinets. MCC room has additional free space available.
4. Can you please confirm which NEC section is applicable for installation location of switchegar ? I want to know what NEC says for installing switchegar inside MCC room along with other distribution panel (powered by a different transformer source) and drive cabinets or the switchgear must be installed in a separate switchegar room ?
Thanks !
I'm planning to install a 13.2 kV/ 480 Volt 2500 KVA transformer, 3000 Amp switchgear (480 V) and 6 VFD drive cabinets.
1. 13.2 kV/ 480 Volt, 2500 KVA transformer will be located outside the manufacturing plant. This transformer will feed a 3000 Amp switchgear rated for 480 V.
2. This switchgear has 6 breakers that will feed 6 drive cabinets. All 6 drive cabinets will be installed inside a MCC room.
3. My question is regarding switchgear installation location. Is it acceptable to install this 3000 Amp switchgear inside MCC room or does it have to be installed in a separate switchgear room ? Please note that MCC room already has a Distribution Panel (DP) fed by another transformer/ switchgear. In addition, MCC room will have many drive cabinets. MCC room has additional free space available.
4. Can you please confirm which NEC section is applicable for installation location of switchegar ? I want to know what NEC says for installing switchegar inside MCC room along with other distribution panel (powered by a different transformer source) and drive cabinets or the switchgear must be installed in a separate switchegar room ?
Thanks !