PresterJohn
Member
- Location
- Pacific North West
- Occupation
- Agrivoltaics
Here's the general idea:
Doing an agrivoltaic installation for distributed generation, got some panels (VSUN550-144BMH-DG), got some inverters (SE5000H). Didn't realize Solaredge inverters require optimizers. In the process procuring them (S1201).
My background:
I'm working for a startup and due to the nature of them (shoestring budgets) I got put on figuring out procurement/design our EE guy has given some guidance on. He doesn't have much of a solar background and subsequently had no idea Solaredge inverters need optimizers in order to function. All he was focusing on was the input/output of the inverter and our design (12 panels per inverter and single phase output required by the utility). So now we've got a bunch of inverters but no optimizers, but I'm being asked to figure out a way to minimize the number of optimizers needed in order to have the inverters function. After digging around and reading a lot of posts on this forum, I figured I'd ask you all for some help.
Here's the current scope of the project:
The main focus of this project is not efficient power production. The main focus is a proof of concept for implementing solar on cattle ranches. The project does need to produce power. The current budget for the project is very limited.
Here are my questions/problems:
If I have 12 panels in an array (A1) and I connect 1 panel (P1) of the array to an optimizer (O1) and connect O1 to an inverter (I1) can I connect the rest of the panels in array A1 to inverter I1 without any connection to any other optimizers?
Also it appears that SE has features within their optimizers which have their systems compliant with NEC rapid shutdown requirements. Would connecting panels to an inverter that didn't have optimizers (but having at least 1 panel with an optimizer going to the inverter) negate or compromise these safety features?
Thanks for any feedback
Doing an agrivoltaic installation for distributed generation, got some panels (VSUN550-144BMH-DG), got some inverters (SE5000H). Didn't realize Solaredge inverters require optimizers. In the process procuring them (S1201).
My background:
I'm working for a startup and due to the nature of them (shoestring budgets) I got put on figuring out procurement/design our EE guy has given some guidance on. He doesn't have much of a solar background and subsequently had no idea Solaredge inverters need optimizers in order to function. All he was focusing on was the input/output of the inverter and our design (12 panels per inverter and single phase output required by the utility). So now we've got a bunch of inverters but no optimizers, but I'm being asked to figure out a way to minimize the number of optimizers needed in order to have the inverters function. After digging around and reading a lot of posts on this forum, I figured I'd ask you all for some help.
Here's the current scope of the project:
The main focus of this project is not efficient power production. The main focus is a proof of concept for implementing solar on cattle ranches. The project does need to produce power. The current budget for the project is very limited.
Here are my questions/problems:
If I have 12 panels in an array (A1) and I connect 1 panel (P1) of the array to an optimizer (O1) and connect O1 to an inverter (I1) can I connect the rest of the panels in array A1 to inverter I1 without any connection to any other optimizers?
Also it appears that SE has features within their optimizers which have their systems compliant with NEC rapid shutdown requirements. Would connecting panels to an inverter that didn't have optimizers (but having at least 1 panel with an optimizer going to the inverter) negate or compromise these safety features?
Thanks for any feedback