customer asked we bid the temp power for new construction but other company is doing construction work is that a normal operation. I would think contractor would want electrical to be done by same EC
I actually do, well not rent by the month, but have about 20 poles set with temp power and 2 quad boxes. Seems digging a t pole has been almost a daily activity lately.