gentlemen,can someone please help with this code question.
I have an existing 400a fusible switch presently serving a 100 kvar
capacitor(its the only available switch in a multiple main swbd)
Can i relocate the capacitor adjacent to the existing location which i now will use as a tap box, and in addition extend the feeder from the tap box to a 225kva 480/120/208v transformer a distance away.If i use 400a wire
throughout and fuse the switch at 400a do i or dont i need secondary
disconnect switches (200a for the capacitor and 400a for the 225kva xfmr)