Tapping Riser

Status
Not open for further replies.
Sounds tricky, but maybe not. If you are physically cutting a new tap box into an existing riser, that may be a challenge in itself. You may need to support the vertical conductors that are below the box. I would recommend a mounted connection block with a cover, not the floating insulated variety your link took me to.

https://commerce.ilsco.com/e2wShopp...d=3100012318&parentLink=2100001183:3100012318

In order to accomplish this without replacing any of the conductors, it's going to be a challenge but not necessarily impossible. You must complete the parallel wiring on the existing sets of conductors, then tap each parallel connected set.
 
You'll need a 3 port Polaris or some other type of connector for three conductors. The #3 EGC with the tap conductors is likely too small.
 
Sounds tricky, but maybe not. If you are physically cutting a new tap box into an existing riser, that may be a challenge in itself. You may need to support the vertical conductors that are below the box. I would recommend a mounted connection block with a cover, not the floating insulated variety your link took me to.

https://commerce.ilsco.com/e2wShopp...d=3100012318&parentLink=2100001183:3100012318

In order to accomplish this without replacing any of the conductors, it's going to be a challenge but not necessarily impossible. You must complete the parallel wiring on the existing sets of conductors, then tap each parallel connected set.

Agreed. So in my mind this is what happens.
1. Install new 3-1/2" pipe and wire to point near new splice box and new panel
2. Shutdown power to existing feeders we are tapping.
3. Cut existing riser conduits/feeders, support feeders.
4. Cut in new splice box.
5. Finish new 3-1/2" conduit install and splice/terminate.

Sound right? Thanks.
 
Agreed. So in my mind this is what happens.
1. Install new 3-1/2" pipe and wire to point near new splice box and new panel
2. Shutdown power to existing feeders we are tapping.
3. Cut existing riser conduits/feeders, support feeders.
4. Cut in new splice box.
5. Finish new 3-1/2" conduit install and splice/terminate.

Sound right? Thanks.

I think you are on the right track, I would allow for some adversity.............
 
You'll need a 3 port Polaris or some other type of connector for three conductors. The #3 EGC with the tap conductors is likely too small.
If the existing is a parallel run, then a 5 port connector would be needed, right?
2 in, 2 out and the tap.
Oops, yes you're correct, a 5 port is needed since the riser is continuing.
Need to know what's in EMDP-G5-42-MSB-2S1.

One of these might work better: https://commerce.ilsco.com/e2wShopp...k=2100001183:3100012178:3100012237:3100012714
 
Status
Not open for further replies.
Top