Toros
Senior Member
- Location
- Tujunga, CA
Hi
Commercial inspector wants us
to show calc. for roof mounted 200A feeder of air condition sub panel with total load of 110A
.
feeder: 2" EMT, (3) 3/0 THHN, Cu + EQ.GR (off a 75 deg. terminal , 200A/3p cir. breaker)
if it was a more than three hot conductors, then I would calculate so;
200A x .75 (per 310.16) = 150A
i am still fine, no need to increase the conductor size.
What do you think??
Thank you
Commercial inspector wants us
to show calc. for roof mounted 200A feeder of air condition sub panel with total load of 110A
.
feeder: 2" EMT, (3) 3/0 THHN, Cu + EQ.GR (off a 75 deg. terminal , 200A/3p cir. breaker)
if it was a more than three hot conductors, then I would calculate so;
200A x .75 (per 310.16) = 150A
i am still fine, no need to increase the conductor size.
What do you think??
Thank you