temp. power grounding grounding question

Status
Not open for further replies.

jcdc

New member
on a constn site, i have a temp. power 480v feeder (about 50' away) which is routed to the building (which is under constn, its going to be a central energy plant). the feeder is routed with 3hots and 1gnd to the primary of a transformer (still temp. power). at the secondary of the transformer the ground is bonded to the neutral and a ground rod is installed; and there is a panelboard on the secondary of the transformer.
the new building is under construction, early stages. there is lots of exposed rebar for future concrete flooring to be poured in a few weeks/months, also vertical rebar for concrete columns.
QUESTION: shouldn't the rebar/metal system be bonded to the ground on the secondary of the transformer (for temp. power) for safety during construction? i'm thinking if a lightning strikes a rebar sticking up in the air -- there will be a difference in potential between the rebar system and the temp. power system.
any thoughts/advice?
 
jcdc, welcome to the forum.

If you know where your new electrical service is going to the building get a concrete encased type electrode (CEE/ufer per 250.52(A)(3)) installed now at this location. Then put your temp power transformer at this same location and bond its electrode to the CEE.
 
Status
Not open for further replies.
Top