temp wiring

Status
Not open for further replies.

mltech

Senior Member
Location
Ft. Lauderdale
What code would prevent me from running an 1 1/4 schedule 40 conduit on top of the ground for a 100a temporary connection for possibly 2 years as construction progresses?
Any help is greatly appreciated.
Mike
 
What code would prevent me from running an 1 1/4 schedule 40 conduit on top of the ground for a 100a temporary connection for possibly 2 years as construction progresses?
Any help is greatly appreciated.
Mike
IMO, if the PVC is protected from damage then I don't see a violation however I would not leave a conduit just sitting on the ground for 2 years. What is the surface? Can you trench it in?
 
IMO, if the PVC is protected from damage then I don't see a violation however I would not leave a conduit just sitting on the ground for 2 years. What is the surface? Can you trench it in?

It is a highly wooded and brushy area and the owner does not want to disturb the plants and such. But wants to use the overhead temporary construction service to back feed a detached garage 100' away.
Thanks again for your help.
Mike
 
It is a highly wooded and brushy area and the owner does not want to disturb the plants and such. But wants to use the overhead temporary construction service to back feed a detached garage 100' away.
Thanks again for your help.
Mike

I would drive a few support stakes and strap the pipe to it and be done with it. If it is out of the way it should not be an issue.
 
Status
Not open for further replies.
Top