Currently I have a 150 amp service with meter pan outside and the main service panel inside. The main service panel is the only disconnect on the system and is grounded and bonded.
I am starting a major construction project and need to temporarily relocate the electric service entrance. It will be approximately 12 feet away from the main service panel. Because of this distance and the need to add some additional temporary power outside, I want to install a outdoor load center next to my meter pan to act as a disconnect.
Is it ok to bond the nuetral in the outdoor load center and in the main service panel inside or do I need to unbond the nuetral on the inside panel as if it were a sub panel. I don't want to If I don't have to.
I am starting a major construction project and need to temporarily relocate the electric service entrance. It will be approximately 12 feet away from the main service panel. Because of this distance and the need to add some additional temporary power outside, I want to install a outdoor load center next to my meter pan to act as a disconnect.
Is it ok to bond the nuetral in the outdoor load center and in the main service panel inside or do I need to unbond the nuetral on the inside panel as if it were a sub panel. I don't want to If I don't have to.