DansProfElec
Member
- Location
- Huntington beach, CA
I have a commercial project upgrading the existing 1200 Amp 120/208 switchgear with new equipment, but need to keep the 6 existing tenants up and running while we remove the existing equipment and install the new switchgear. The problem comes with providing a temporary power solution that doesn't cost as much as the whole upgrade. All the upgrades we have done to date were on projects were no tenants were present, so temp power was simple.
SDG&E (San Diego Gas & Electric) will give us (max) 400 amps out of their transformer. All the subpanels in the 6 suites are flush mounted, bottom fed through conduit under the fondation. Half of the panels are burried in rooms that are hard to get to. Subpanels are rated (1 - 200 Amp, 2 150 Amp, 3 - 100 Amp subpanels). The total building measured load for any one phase is under 250 Amps.
I had the city head Electrical inspector and the SDG&E Sr. Planner on site and they were scraching their heads on how to go about it. The SDG&E Planner wanted us to install a 400 Amp main disconnect with meter socket and with 6 main breakers (at a cost of about $8,000.00) I'm trying to get him to agree to use 2 200 amp meter panels and find a over the roof connection method (the trans fomer is within 60 feet of the building.
If anyone has some experienc with the same kind of problem of hooking up the 6 subpanels (by top feed) in the suites to temporary power I would love to hear.
Dan
SDG&E (San Diego Gas & Electric) will give us (max) 400 amps out of their transformer. All the subpanels in the 6 suites are flush mounted, bottom fed through conduit under the fondation. Half of the panels are burried in rooms that are hard to get to. Subpanels are rated (1 - 200 Amp, 2 150 Amp, 3 - 100 Amp subpanels). The total building measured load for any one phase is under 250 Amps.
I had the city head Electrical inspector and the SDG&E Sr. Planner on site and they were scraching their heads on how to go about it. The SDG&E Planner wanted us to install a 400 Amp main disconnect with meter socket and with 6 main breakers (at a cost of about $8,000.00) I'm trying to get him to agree to use 2 200 amp meter panels and find a over the roof connection method (the trans fomer is within 60 feet of the building.
If anyone has some experienc with the same kind of problem of hooking up the 6 subpanels (by top feed) in the suites to temporary power I would love to hear.
Dan