Michaelriordan
New User
- Location
- glendale, az
- Occupation
- Power generation manager
Hello,
I work in the temporary power industry and am seeking advice on our current power plant setup in California. We have eight 500 kW generators paralleled at an 8000 A paralleling cabinet. The output branches off into two 4000 A breakers, which feed two 2.5 MVA transformers stepping up the voltage from 480 V to 12,470 V.
My question is: Should we place the bond at the paralleling cabinet or at the transformers, rather than at the generators?
I work in the temporary power industry and am seeking advice on our current power plant setup in California. We have eight 500 kW generators paralleled at an 8000 A paralleling cabinet. The output branches off into two 4000 A breakers, which feed two 2.5 MVA transformers stepping up the voltage from 480 V to 12,470 V.
My question is: Should we place the bond at the paralleling cabinet or at the transformers, rather than at the generators?