In our industrial construction, often times we are required to run temporary power for offices, lunch tents, etc. underground. We have had instances where these underground cables have been struck while other trenching has been done.
Is there any place in the NEC that covers underground temporary power cable burial requirements? Does NEC differentiate the difference between temporary and permanent underground cable installations?
Thanks
Is there any place in the NEC that covers underground temporary power cable burial requirements? Does NEC differentiate the difference between temporary and permanent underground cable installations?
Thanks