Hi Everyone,
I’m currently working on a project where we are installing a standby generator in a dedicated room within an existing sewage lift station building. The existing MCC is equipped with an ASCO 7000 Automatic Transfer Switch, and the new generator will be a Cummins model. I have attached a photo of the transfer switch controls and indicators.
Before the generator is connected and commissioned, I want to test the functionality of the ASCO 7000 ATS. Could anyone advise on how to properly test or simulate the ATS operation without having the standby generator physically connected?
Any tips on safely verifying the ATS logic, transfer mechanism, and start signals would be greatly appreciated!
Thanks in advance.
I’m currently working on a project where we are installing a standby generator in a dedicated room within an existing sewage lift station building. The existing MCC is equipped with an ASCO 7000 Automatic Transfer Switch, and the new generator will be a Cummins model. I have attached a photo of the transfer switch controls and indicators.
Before the generator is connected and commissioned, I want to test the functionality of the ASCO 7000 ATS. Could anyone advise on how to properly test or simulate the ATS operation without having the standby generator physically connected?
Any tips on safely verifying the ATS logic, transfer mechanism, and start signals would be greatly appreciated!
Thanks in advance.