I am on a job that the total length of the pull is 600' with a pull box at 300'. The contractor is pulling (3) 2/0 and one #2 in a two inch PVC. The conduit fill is OK per NEC. But the to pull will be really hard. (IMO) He is not willing to listen and increase the size to minimum 3"
I have not done a pull this long but just reading on this forum I know it will be a tough pull.
Is there a pull calculator that will show some numbers. Maybe I can convince him if he sees the numbers on the calculator. Then again I am thinking let him do it it is not any of my business.
I have not done a pull this long but just reading on this forum I know it will be a tough pull.
Is there a pull calculator that will show some numbers. Maybe I can convince him if he sees the numbers on the calculator. Then again I am thinking let him do it it is not any of my business.