crfmario
Member
- Location
- snohomish, washington
Hey guys my question is, I am adding power to a subpanel in a 40 ft cargo container at an asphalt plant (just for lights and plugs) but the way I have been told to do it concerns me because Im wondering if it is wrong. I need to come off of a 3phase 480v 50amp breaker to feed a basic single phase, 100amp 120/240 sub panel, but my boss told me to use a 30kva 3phase transformer that he had laying around his shop. If I bring three phase 480 to this disconnect then to the transformer, can I just come off of 2 of the secondary lugs (instead of using all three) to feed my single phase subpanel? I feel like I could get away with it but that it isnt right, and i understand that I could potentially throw the system off balance by doing this. Anyhow , hopefully I described my situation in enough detail to understand. I feel like its kind of an amateur question but its buggin me pretty bad. Any and all input is greatly appreciated