mshields
Senior Member
- Location
- Boston, MA
Life Safety and Critical have to come on in 10 seconds (although now that critical is divored from Article 700, I'm not sure that's any longer defined - is it).
But my real question concerns the Equipment branch. 517 talks about automatic connection to generator and certain loads which may be manually switched over, but I don't see a time frame for the former of these? Is it in FNAP 99 by chance? Or is it in the NEC and I'm missing it?
Thanks,
Mike
But my real question concerns the Equipment branch. 517 talks about automatic connection to generator and certain loads which may be manually switched over, but I don't see a time frame for the former of these? Is it in FNAP 99 by chance? Or is it in the NEC and I'm missing it?
Thanks,
Mike