pedorrero79
Member
Hi all,
I have a question regarding sizing a transformer. The situation is this: a new building is being built and the owner is going from a 240V/1-phase service to 480V/3-phase service. However, they have an existing air compressor that they're going to move to the new facility but the air compressor is rated for 240V only. What we're planning to do is have a branch circuit from a 480V panel to a 480:240 transformer and feed the air compressor from there. (I know it's simpler for them to buy a new compressor but they're adamant about keeping this one because it's relatively new.)
I've determined the load that the compressor will put on the system (4,320VA) and think I need a 5kVA transformer. However, my question is: should the transformer be upsized to take into account the inrush current of the compressor?
Any and all help is appreciated.
Thanks,
- P
I have a question regarding sizing a transformer. The situation is this: a new building is being built and the owner is going from a 240V/1-phase service to 480V/3-phase service. However, they have an existing air compressor that they're going to move to the new facility but the air compressor is rated for 240V only. What we're planning to do is have a branch circuit from a 480V panel to a 480:240 transformer and feed the air compressor from there. (I know it's simpler for them to buy a new compressor but they're adamant about keeping this one because it's relatively new.)
I've determined the load that the compressor will put on the system (4,320VA) and think I need a 5kVA transformer. However, my question is: should the transformer be upsized to take into account the inrush current of the compressor?
Any and all help is appreciated.
Thanks,
- P