big john
Senior Member
- Location
- Portland, ME
When bringing the GEC out of a transformer, does it have to be bonded at the point where it passes through the metal transformer enclosure? (I know it's a good idea, but not sure if it's required.)
250.64(E) says to bond each end of the enclosure... So do I count the point where the GEC is connected to the SDS as one "end" of the enclosure and then bond as it leaves the transformer through the other "end" of the enclosure?
Thanks a bunch.
-John
250.64(E) says to bond each end of the enclosure... So do I count the point where the GEC is connected to the SDS as one "end" of the enclosure and then bond as it leaves the transformer through the other "end" of the enclosure?
Thanks a bunch.
-John