rnsd
New member
- Location
- San Diego, CA USA
I have a 75KVA 208:480/277V transformer that is only about half loaded so the primary conductors are downsized to 3/0 and protected by a 200A breaker. I am using ETAP to model this and the protective device coordination analysis shows that there may be some nuisance tripping of this circuit breaker as the transformer inrush current on the TCC is being calculated at 8X the FLA of the rating of the transformer (208.2A). Is this ETAP defaulted 8x of the FLA of the transformer a standard calculation or can this be less than 8X?
Thanks
Thanks