j00111581
Member
- Location
- Mobile, AL, USA
We currently have a project that is fed with an exterior Nema 3R main panel and an exterior Nema 3R 225 kva transformer. The owners have a need to expand the mechanical room on the end of the building where this electrical equipment is located. In lieu of moving all of the equipment they wanted to know if they could building the room around the panel and transformer and just relocate the meter to the exterior wall of the new expansion. Is there any reason (clearance, ventilation, code, etc.) that would prevent this from being ok?