Just want to run my configuration by others to see if im missing something as im new to the transformer game.
I am running 480V feeders sized for 125A into a fused disconnect w/100A Fuses.
From there I am running into a 75KVA transformer then into a 200A 120/208v Main breaker panel.
Im just wondering if this looks good , I wasnt sure if i could run secondaries straight onto the main breaker