engineer84
Member
I am installing a 50 kva delta to wye transformer on the secondary side for grounding I have the following:
X0 tap--- 1) neutral to machine
2) ground wire to lug on frame
Frame ground bar--- 1) system ground from bus duct
2) ground to machine
3) ground to building steel
4) ground wire to X0
Is this acceptable? Any advice?
X0 tap--- 1) neutral to machine
2) ground wire to lug on frame
Frame ground bar--- 1) system ground from bus duct
2) ground to machine
3) ground to building steel
4) ground wire to X0
Is this acceptable? Any advice?