I have a 400 amp disconnect. I need to run a 60 ft. run of 3/0 from this disconnect to a 200 amp main breaker load center. From this same 400 amp disconnect, I need to run a 70 ft run of 3/0 to another 200 amp main breaker load center.
Does code require I set two 200 amp disconnects within 10 ft. of the 400 amp disconnect and then make my runs from them? OR can I just come directly off the 400 amp disconnect?
I am a little fuzzy on this. 10 ft. tap rule is giving me trouble understanding????
Does code require I set two 200 amp disconnects within 10 ft. of the 400 amp disconnect and then make my runs from them? OR can I just come directly off the 400 amp disconnect?
I am a little fuzzy on this. 10 ft. tap rule is giving me trouble understanding????