I have this compound of about one and half plot of land hosting two buildings, the first building is completed with proper grounding/earthing done and occupied fully by tenants. Now the second building is still in completion stage; the question now is, do I need a separate grounding/earthing for this second building?
 

charlie b

Moderator
Staff member
Location
Lockport, IL
Occupation
Retired Electrical Engineer
Are you asking if you can connect the second building's service neutral to the grounding electrode system of the first building?
 

Bukadans

Member
Location
Nigeria
Occupation
Electrical Engineer
Are you asking if you can connect the second building's service neutral to the grounding electrode system of the first building?
I am asking to know if it is necessary to carry out entily a separate grounding for the second building since they are more like a twine building.
Note, the first building has thunder spike.
 

charlie b

Moderator
Staff member
Location
Lockport, IL
Occupation
Retired Electrical Engineer
I will need other opinions on this one. I believe that it is not allowed, that the second building needs its own, independent, grounding electrode system. But I can't cite a specific code article to confirm that believe. Anyone want to chime in?

What is a thunder spike?
 

roger

Moderator
Staff member
Location
Fl
Occupation
Retired Electrician
Is Nigeria's electrical system the same as we use here and would the NEC apply?
 

packersparky

Senior Member
Location
Wisconsin
Occupation
Inspector
I will need other opinions on this one. I believe that it is not allowed, that the second building needs its own, independent, grounding electrode system. But I can't cite a specific code article to confirm that believe. Anyone want to chime in?

What is a thunder spike?

Ground rod, maybe?
 

Bukadans

Member
Location
Nigeria
Occupation
Electrical Engineer
I will need other opinions on this one. I believe that it is not allowed, that the second building needs its own, independent, grounding electrode system. But I can't cite a specific code article to confirm that believe. Anyone want to chime in?

What is a thunder spike?
The lightning arrester placed at the top of the roof.
 