Working on a project out of the continental US in a US territory. There is an existing building with a 200A SER ATS and a new building being built adjacent to it which will also require a 200A service and will also have a 200A SER ATS. This will most likely end up being a 100 kW diesel generator but im trying to figure out how to feed each individual transfer switch. Would there just be a tap inside the generator itself?? I know this is done all the time for campuses but I havent personally worked on one before. Also, if one building loses power how would the generator know to start?