Nothing's shocking
Member
- Location
- Holbrook, MA USA
I'm doing a service upgrade on a two family with two 60A panels. They want to add circuits (pool, kitchen remodel ) but panels are maxed. I was going to
give them each 100 A panels. Load calcs are below that due to gas appliances and heat in the units. If I drop a 200 A service into a 2 gang meter, do I need
to install 200 A panels or just go by my calcs?
give them each 100 A panels. Load calcs are below that due to gas appliances and heat in the units. If I drop a 200 A service into a 2 gang meter, do I need
to install 200 A panels or just go by my calcs?