sparky 134
Senior Member
- Location
- Joliet, IL
The GC is asking me to produce two final lien waivers for a project, one for the electrical and one for the fire alarm. I only have one contract for both. I explained that I cannot create two separate waivers as one would invalidate the other. He countered with he has me listed separately on his contractors affadavit.
I submitted one final waiver and under the column of work performed I listed electrical on the first line with a dollar amount and fire alarm on the second line with a dollar amount. He rejected it saying he needs two separate waivers.
I'm refusing to do so. My reasoning is if I'm not paid for one of the waivers and I lien the project the lien would be dismissed because of the other waiver.
Has anyone else encountered this situation ?
I submitted one final waiver and under the column of work performed I listed electrical on the first line with a dollar amount and fire alarm on the second line with a dollar amount. He rejected it saying he needs two separate waivers.
I'm refusing to do so. My reasoning is if I'm not paid for one of the waivers and I lien the project the lien would be dismissed because of the other waiver.
Has anyone else encountered this situation ?