Let's say:
1. Temporary Power for construction site.
The incoming power to the meter is set with 2" rigid conduit overhead with L1,L2,N. Is required to run grounding conductor in the incoming power?
2. Permanent Power.
Two runs 4" with 3-750kcmil (L1,L2,L3) +1-750kcmil (N)each. Is required to run grounding conductor with the service entrance conductors from de Pad mounted Transformer to the Main Distribution Panel?
1. Temporary Power for construction site.
The incoming power to the meter is set with 2" rigid conduit overhead with L1,L2,N. Is required to run grounding conductor in the incoming power?
2. Permanent Power.
Two runs 4" with 3-750kcmil (L1,L2,L3) +1-750kcmil (N)each. Is required to run grounding conductor with the service entrance conductors from de Pad mounted Transformer to the Main Distribution Panel?