slc410
Electrician
- Location
- Madison wi
- Occupation
- Electrician
An addition was added to a commercial building I'm on and the inspector requested us to install a ufer ground in the addition. The existing building is the same build structure (concrete block and steel structure) . Am I required that ufer conductor to go all the way back (150') to the panel with main disconnect or can I just bond it to building steel which is all tied to existing steel structure?