J Joao Member Location portugal Occupation engineer May 15, 2025 #1 Is there any standard that refers minimum distance between UHV/EHV Cables and Coke/Blast Furnace Gas? Any EMC study must be done?
Is there any standard that refers minimum distance between UHV/EHV Cables and Coke/Blast Furnace Gas? Any EMC study must be done?
Julius Right Senior Member Occupation Electrical Engineer Power Station Physical Design Retired May 19, 2025 #2 In my opinion, you should see: NEC art.503.10 for wiring above coke field. NESC Rule 234. Clearance of wires, conductors, cables, and equipment from buildings, bridges, rail cars, swimming pools, and other installations
In my opinion, you should see: NEC art.503.10 for wiring above coke field. NESC Rule 234. Clearance of wires, conductors, cables, and equipment from buildings, bridges, rail cars, swimming pools, and other installations