Member
I need to build some panels and customer is asking they be UL labeled. Does anyone know the process and who I might need to contact?
Thanks, bob
Thanks, bob
I need to build some panels and customer is asking they be UL labeled. Does anyone know the process and who I might need to contact?
Thanks, bob
I need to build some panels and customer is asking they be UL labeled. Does anyone know the process and who I might need to contact?
Thanks, bob
And just to add to this, the process of ATTAINING a UL 508A listing capability for your shop will take you around 6 months and, last time I helped someone with it about 2 years ago, around $20,000 by the time it is all done. So if it is just one or a few panels, find a UL 508A panel shop to build them for you. If you want to go into the business of BECOMING a UL 508A panel shop, and your customer can wait that long, then look into the option with UL.the simplest and most cost effective solution is to just have them built by a UL shop.
they will also need to be properly designed to UL standards.
there is nothing real special about designing to UL standards but now and then you can get tripped up if you are not real familiar with all of the requirements.