hhsting
Senior Member
- Location
- Glen bunie, md, us
- Occupation
- Junior plan reviewer
I have underground metal water pipe as grounding electrode. It has water meter/filter device right where it enters little beyond 5 feet like 6 feet. I am required to provide bonding jumper per NEC 2014 section 250.53(D)(1).
I did research I would imagine this is equipment bonding jumper right at the service disconnect. However not sure. Would it be supply side bonding jumper.
Which table one uses to size the bonding jumper and where is it in code?
I did research I would imagine this is equipment bonding jumper right at the service disconnect. However not sure. Would it be supply side bonding jumper.
Which table one uses to size the bonding jumper and where is it in code?
Last edited: