I am working at a plant trying to install u/g from the MCC room to the motors in the field. We have approx. 70 motors, the smallest are 1HP the largert are 250HP. ( sorry but this will take a little explaning ) The MCC room feeds motors in 2 seperate buildings, in the first building the longest motor is around 200'. The second building conduit runs through the first building and an additional 200' for a total of 400'. All the motors are 480V. The Problem----- My eng. are telling me that in an u/g duct bank I can only install 15 motors. Before we have to start derating. ( alot ) The next duct bank has to be 5' away from the first (that is center line of D.B.) and can still only have 15 motors. ( can you see my problem??) I will have to have five duct banks breaking out from the MCC room. This is not possible. Has anyone had problems with this, is their any exceptions to this???? Please help Also what makes a duct bank 2 conduits or 10 ???? Thanks for your time.