601John
Member
- Location
- kermit, TX
I am at a sand mine, contractor has installed 4 parallel runs of #350 from 2000 amp main, located outside of MCC, underground, transitioning to cable tray under building. Building is 5 ft off ground. PVC extends about 18" above sand. it goes in free air to tray (aprox 2ft) grouped by pipe, supported on tray, then all wires tied together rising another 18" into building. The plan to seal penetration ( 6x6" square chase) with Duct Seal. Wire is rated for cable tray. No clamps or supports other than tray. This looks wrong in many ways. Superintendent is grouchy old man, instead of having a discussion about it he claims it is right and challenged me to prove him wrong. I need a little help or explanation why it is right.