Hello, I was asked to do a small storage unit. It will be broken down into three phases. I am currently just working on phase 1, with also running underground for phase 2 for the future. The owner wants a sheet showing underground locations. Could you guys tell me if you would feed these building differently.
I did not want any underground to cross but had building AB feed AC so they cross. I thought about AC feeding AD. The AD+AG+AJ is 980 feet for just the building(AJ is on phase 3 so did not include).I wanted to keep that building separate to help with the VD.
This is my first large job that I am doing since I started on my own, so second guessing my self left and right. I have several other question but just this one at the moment.
Thank you guys again.
I am sorry if its small, I will try and fiqure out how to zoom in.
I did not want any underground to cross but had building AB feed AC so they cross. I thought about AC feeding AD. The AD+AG+AJ is 980 feet for just the building(AJ is on phase 3 so did not include).I wanted to keep that building separate to help with the VD.
This is my first large job that I am doing since I started on my own, so second guessing my self left and right. I have several other question but just this one at the moment.
Thank you guys again.
I am sorry if its small, I will try and fiqure out how to zoom in.