nizak

Senior Member
Looking to get some feedback for cost to do the following underground feeder work.
- Install (3) runs of 300 MCM direct burial Al conductors 260’ each
- Install (1) run of 1/0 direct burial Al conductor 260’
- Terminate at both ends of run in 200 A 3R disconnects.
- Both ends sleeved up to disconnects with 4’ stubs of 2.5” Sch 40 PVC

Wire was pulled from individual spools one spool at a time due to inability of setting them all up together because of space limitations.

Trench and backfill was not included in my cost and was provided by the owner.

Trench was 12” wide, 30” deep with (2) 90 degree turns and several minimal bends throughout. Trench route was through wooded ( forest) terrain
Owner paid for the wire. Labor and everything needed was provided in my cost.

I also picked up the wire and transported it to the job. Approximately 2hrs for that.

Looking to get an idea if I’m competitive with a job like this.

Thanks for your time.
 