The POCO I have worked with in the past requires a 30" trench for an underground service. I'm planning an underground service with a different POCO (National Grid) and they only require the trench to be NEC compliant.
As far as i can see NEC only requires 18" per 300.5. True?
Conductors will be in PVC
As far as i can see NEC only requires 18" per 300.5. True?
Conductors will be in PVC