I'm putting a 1200A feeder from the main electrical room in a 2 story, 30,000 sq ft building to the main electrical room for one of it's tenants. I'm stuck with putting it under the slab due to conversations/agreements made before I cam on boards. The tenant happens to be an Ambulatory Surgery Center. I'm looking for input on how best to run this feeder under the slab. My inclination is to do it in direct burried RGS. Am I over doing it? underdoing it? What do you think?